Consider the supply chain planning implementation project depicted in Figure 15S-1. Suppose…

Consider the supply chain planning implementation project depicted in Figure 15S-1. Suppose…

Consider the supply chain planning implementation project depicted in Figure 15S-1. Suppose that the client has offered a $4,000 bonus to us if we can complete the project seven working days early. Based upon the crash cost information provided in Table 15S1, would you accept the client’s proposal? By how many days could you profitably shorten the project?

 